Site Management Workshop & The big test


A role-playing simulation was conducted in the classroom about the handling of ground stoppages during an epidemic.


The big test


The Contractor lets you (landscape architect) know that all planting works on a landscape project for which you are primarily responsible are now complete. Which of the following statements are CORRECT ?


Any planting works that are defective must be replaced before the client can move onto the site. X

Client can move onto the site following issue of Certificate of Practical Completion.


The DLP can only commence for the completed section of works once a Certificate of Practical Completion is issued for it.